Feature Flag Tracking Dashboard

Tracking the 314 remaining 1JS-related flags from ADO item creation through stakeholder review and final removal.

Cycle windowSep 28, 2026 — Jan 8, 2027

Overall Cleanup Progress

New In Progress Complete
314flags this cycle
Hover over a segment for details

Execution Health

Good ≥ 100% of plan

Delayed 80–99% of plan

At Risk < 80% of plan

Plan = minimum flags that should be complete by today.

Elapsed cycle

Workdays = Mon–Fri, excluding Nov 26–27, Dec 24–25 and Jan 1. Today counts as elapsed.

Minimum complete by today
Actually complete
Gap to plan
Remaining flags
Remaining time
Required weekly pace

Weekly pace = remaining flags ÷ remaining workdays × 5, rounded up.

of plan

ADO Items Created by Week

In Progress Complete

Engineer Impact

Weekly star = the engineer completed that week’s removal target.

Engineers stay in a fixed order; completed-item counts are not used for ranking.

Impact nomination = stars in at least 90% of eligible weeks. Thanksgiving week and the two Christmas weeks are excluded.

Week 2Oct 5 — Oct 11

Team Award

Team weekly star = total team completions reached that week’s Required Weekly Pace.

Mixed Award Nomination = the team earned stars in at least 90% of remaining eligible weeks.

Thanksgiving week and the two Christmas weeks are excluded.

A shared goal that recognizes the team’s collective delivery. Everyone contributes to the same weekly pace and celebrates the same result.

In progressMixed Award Nomination
0 of — required stars earned 90% of — eligible weeks